File #: 15-0765    Version: 1 Name: PSA Hethcoat Davis Goose Creek Extension
Type: Contract/Agreement Status: Passed
File created: 8/14/2015 In control: Board of Mayor & Aldermen
On agenda: 9/8/2015 Final action: 9/8/2015
Title: Consideration of Amendment No. 1 to the Professional Services Agreement (COF Contract No. 2014-0177) with Hethcoat & Davis, Inc. for the Goose Creek Sanitary Sewer Extension Project from West of I-65 to the East Side of I-65 Improvements Project at a cost INCREASE of $11,810.00 (08/27/15 CIC 3-0)
Sponsors: Engineering
Attachments: 1. COF 2014-0177 PSA Amendment1 GooseCreekSewer ExhibitA.pdf, 2. COF 2014-0177 Amend 1 Hethcoat & Davis Final.pdf

 

DATE:                                                               August 27, 2015

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          David Parker, City Engineer/CIP Executive

                                          Mark Hilty, Director of Water Management

                                          Paul Holzen, Director of Engineering

                                          Patricia McNeese, Utilities Project Manager                     

                     

SUBJECT:                                          

title

Consideration of Amendment No. 1 to the Professional Services Agreement (COF Contract No. 2014-0177) with Hethcoat & Davis, Inc. for the Goose Creek Sanitary Sewer Extension Project from West of I-65 to the East Side of I-65 Improvements Project at a cost INCREASE of $11,810.00 (08/27/15 CIC 3-0) 

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning a proposal from Hethcoat & Davis, Inc. to modify their existing Professional Services Agreement for the Goose Creek Sanitary Sewer Extension Project from West of I-65 to the East Side of I-65 Improvements Project.

 

Background

On September 9, 2014, the Board of Mayor and Aldermen approved a Professional Services Agreement (COF Contract No. 2014-0177) with Hethcoat & Davis, Inc. for the preliminary engineering of the Goose Creek Sanitary Sewer Extension Project from West of I-65 to the East Side of I-65 Improvements Project.  This professional services agreement, at a cost of $120,725.00, allowed Hethcoat & Davis, Inc. to provide the City with a detailed plan to extend sanitary sewer across I-65.  During the design process, it was suggested that the reclaimed water line should be extended to parallel the proposed gravity sanitary sewer line, as shown in the Reclaimed Water Master Plan.  This proposed amendment would include the reclaimed water design in with the existing sewer extension project.

 

Financial Impact

The original Professional Services Agreement (COF Contract No. 2014-0177) with Hethcoat & Davis, Inc. was at a not-to-exceed cost of $120,725.00. 

 

Amendment No. 1 to the Professional Services Agreement (COF Contract No. 2014-0177) with Hethcoat & Davis, Inc. is in the amount of $11,810.00. This creates a new not-to-exceed total contract cost $132,535.00.  All costs will be paid for out of the FY2015-2016 Sewer Operating Fund.

 

Recommendation

rec

Staff recommends approval of Amendment No. 1 to the Professional Services Agreement (COF Contract No. 2014-0177) with Hethcoat & Davis, Inc.