File #: 15-0985    Version: 1 Name:
Type: Report Status: Agenda Ready
File created: 10/16/2015 In control: Capital Investment Committee
On agenda: 10/29/2015 Final action:
Title: Water and Sewer Projects Status Report
Sponsors: Engineering
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

DATE:                                                               October 29, 2015

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                                               David Parker, City Engineer/CIP Executive

Mark Hilty, Director of Water Management

Paul Holzen, Director of Engineering

 

SUBJECT:                                          

title

Water and Sewer Projects Status Report

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City’s water and sewer projects.

 

Project Status

A.                     Spencer Creek Basin - South Prong Interceptor Upgrade

Key Dates: Design Start - April 23, 2013; Design Completion - November 2015*; Bid Date: Not Funded; Construction Start - Not Funded; Construction Completion - Not Funded

*Denotes Estimated Date

Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded

Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD

Status Update:  Design plans are still being developed and are approximately 75% complete.  The project will not be constructed until funding is available from the Water Management Department budget.

 

B.                     Spencer Creek at Franklin Road Sewer

Key Dates: Design Start - March 11, 2014; Design Completion - June 2015; Easement Acquisition Start - September 2015*; Easement Acquisition Completion - November 2015*; Bid Date: January 2016*; Construction Start - March 2016*; Construction Completion - September 2016*

                     *Denotes Estimated Date

Cost: Design - $40,000.00; Easement - TBD; Construction - TBD

Funding Source: Design - Sewer Fund

Status Update:  The plans are 100% complete.  Easement acquisition will begin after the appraisals are completed.

 

C.                     Curd Branch and Watson Branch Interceptor Sewer

Key Dates: Design Start - February 25, 2014; Design Completion - September 2015; Easement Acquisition Start - February 2015; Easement Acquisition Completion - November 2015*; Bid Date: January 2016*; Construction Start -March 2016*; Construction Completion - March 2017*

*Denotes Estimated Date

Cost: Design - $115,000.00; Easement - TBD; Construction - TBD

Funding Source: Design - Sewer Fund

Status Update:  Design plans are 100% complete but plans will not be submitted to TDEC for approval until the easements are obtained.  Condemnation proceedings are beginning on some of the easements which will delay the start of the project.

 

D.                     Fieldstone Farms Pump Station No. 1 Rehabilitation

Key Dates: Design Start - January 14, 2014; Design Completion - November 2014; Bid Date: December 11, 2014; Construction Start - July 2015; Construction Completion - July 2016

Cost: Design - $226,848.00; CEI - $196,000.00; Construction - $1,592,000.00

Funding Source: Design - Sewer Fund; Construction - Sewer Operating Fund

Status Update:  Excavation of the wet well continues.  Once the excavation is complete, the concrete work will begin.

 

E.                     Sanitary Sewer System Model and Capacity Assurance Tool - Phase 1

Key Dates: Design Start - March 11, 2014; Design Completion - August 2015

Cost: Design - $182,000.00

Funding Source: Design - Sewer Fund

Status Update:  Phase 1 is complete.  Staff is currently working on the location of 17 temporary flow monitors to gather data so that Phase 2 can start.

 

F.                     Goose Creek Sanitary Sewer Extension Project from West of I65 to the East Side of I65

Key Dates: Design Start - September 9, 2014; Design Completion - April 2015; Easement Acquisition Start - July 2015*; Easement Acquisition Completion - October 2015*; Bid Date: December 2015*; Construction Start - February 2016*; Construction Completion - August 2016*

*Denotes Estimated Date

Cost: Design - $132,535.00; Easement - TBD; Construction - TBD

Funding Source: Design, Easement, Construction - Sewer Fund & HPT TA Properties Trust

Status Update:  Offers are still being made to the property owners for the easements necessary to construct the project. 

 

G.                     Bobby Drive Water Line Improvement Project

Key Dates: Design Start - May 12, 2015; Design Completion - November 2015; Easement Acquisition Start - December 2015*; Easement Acquisition Completion - April 2016*; Construction Start - June 2016*; Construction Completion - January 2017*

*Denotes Estimated Date

Cost: Design - $80,313.00; Easement - TBD

Funding Source: Design and Easement - Water Operating Fund

Status Update:  Public Meeting to be held on October 29 at 6:00 pm in the Boardroom.  Plans are 80% complete.

 

H.                     Old Carter’s Creek Water Line Improvements

Key Dates: Design Start - May 12, 2015; Design Completion - November 2015; Easement Acquisition Start - December 2015*; Easement Acquisition Completion - March 2016*; Bid Date: April 2016*; Construction Start - June 2016*; Construction Completion - November 2016*

*Denotes Estimated Date

Cost: Design - $79,498.00; Easement - TBD; Construction - TBD

Funding Source: Design, Easement, Construction - Water Operating Fund

Status Update:  The draft technical report has been submitted.  Staff to meet on October 19, 2015 to discuss the results of the report.

 

I.                     James Street and Avondale Street Water and Sanitary Sewer Improvements Project

Key Dates: Design Start - May 12, 2015; Design Completion - November 2015; Bid Date: December 2015*; Construction Start - February 2016*; Construction Completion - October 2016*

*Denotes Estimated Date

Cost: Design - $83,350.00; Construction - TBD

Funding Source: Design and Construction - Water and Sewer Operating Funds

Status Update:  Plans are complete and will be submitted to TDEC for approval before the end of October.  No easements are necessary for this project.