DATE: December 8, 2017
TO: Franklin Municipal Planning Commission
FROM: Joey Bryan, Planner
Amy Diaz-Barriga, Current Planning Supervisor
Emily Hunter, Director of Planning and Sustainability
Subject
title
Rucker Park PUD Subdivision, Site Plan, Phase 2, 6 Attached Residential Units And 1 Open Space Lot, On 0.48 Acres, Located At 117 Rucker Avenue. (CONSENT AGENDA)
body
Project Information
COF Project Number: 6496
Applicant: Greg Gamble, Gamble Design Collaborative
Owner: RBF Investments, LLC, John Franks, Rep.
Background/Staff Comments
The applicant is seeking approval for a site plan for Phase 2 of the Rucker Park PUD Subdivision. The proposed phase is for 6 additional attached units and one open space lot. The Development Plan Revision for this phase of Rucker Park was approved by the Board of Mayor and Aldermen at its November 8, 2016 meeting.
Recommendation
recommendation
Approval, with conditions.
end
See attached pages for a list of staff recommended conditions of approval.
PROCEDURAL REQUIREMENTS:
1. The applicant shall upload the corrected plan to the online plan review website (<https://franklin.contractorsplanroom.com/secure/>). All revisions to the approved plans shall be “clouded.” With the resubmittal, each condition of approval/open issue in the online plan review system shall contain a full response from the applicant as to the satisfaction or completion of that condition.
2. Once the corrected site plan has been approved, one (1) full-size and one (1) half-size copy of the final approved landscape plans shall be submitted to the Department of Building and Neighborhood Services for future landscape inspection purposes.
3. Once the project has obtained Site Plan approval, the applicant will be notified by COF Engineering Department with instructions regarding the status of their digitally stamped construction plans.
4. The applicant shall upload complete building plans, including the approved, revised site plans, to the City's IDT site for Building and Neighborhood Services Department review and approval prior to the issuance of a building permit.
5. Prior to start of any excavation work, the developer and/or contractor shall notify AT&T and Comcast.
6. The city’s project identification number shall be included on all correspondence with any city department relative to this project.