File #: 15-0752    Version: 1 Name: Wilson Pike & East McEwen Drive - Change Order No. 2 (Final)
Type: Contract/Agreement Status: Passed
File created: 8/12/2015 In control: Board of Mayor & Aldermen
On agenda: 9/8/2015 Final action: 9/8/2015
Title: Consideration of Change Order No. 2 (FINAL) to the Construction Contract (COF Contract No. 2012-0145) with Brown Builders, Inc. for the Intersection of State Route 252 (Wilson Pike) and McEwen Drive Project for a time extension and cost DECREASE of $200,469.88 (08/27/15 CIC 3-0)
Sponsors: Engineering
Attachments: 1. McWilson_CONST_CO2_SIGNED.pdf, 2. McWilson_CONST_PMT16.pdf

 

DATE:                                                               August 27, 2015

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          David Parker, City Engineer/CIP Executive

                                          Paul Holzen, Director of Engineering

                                          Jonathan Marston, Staff Engineer 3

                     

                                          

SUBJECT:                                          

title

Consideration of Change Order No. 2 (FINAL) to the Construction Contract (COF Contract No. 2012-0145) with Brown Builders, Inc. for the Intersection of State Route 252 (Wilson Pike) and McEwen Drive Project for a time extension and cost DECREASE of $200,469.88 (08/27/15 CIC 3-0)

body

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Change Order No. 2 (FINAL) to the construction contract (COF Contract No. 2012-0145) with Brown Builders, Inc. (BBI) for the Intersection of State Route 252 (Wilson Pike) and McEwen Drive Project for a time extension and a cost decrease.

 

Background

On October 27, 2012, the BOMA awarded the construction contract (COF Contract No. 2012-0145) for the intersection of Wilson Pike and East McEwen Drive to BBI in the amount of $1,991,572.82.  Because of initial utility delays, the City was not able to issue a Notice to Proceed for construction until July 8, 2013, with an expected substantial completion date of July 8, 2014.  On July 8, 2014, the BOMA approved Change Order No. 1 to this contract for a time extension only.  This time extension allowed for a substantial completion date of October 6, 2014 and established a final payment date of October 31, 2014.  The project was fully opened to traffic in Fall 2014.  Some work continued to stabilize the slopes before the winter months.  Unfortunately, due to a delay by one of the subcontractors, the prime contractor was unable to deliver a final invoice to the City until April 23, 2015.  Change Order No. 2 extends the dates of substantial completion to November 30, 2014 and final payment to April 23, 2015.

 

After tabulating of cost overruns and underruns, there is $200,469.88 ($76,975.92 unused Project Contingency and $123,493.96 line item savings) remaining unspent from the original contract. 

 

Financial Impact

Excluding the original Project Contingency of $150,000.00, there is an actual project savings of $50,469.88, or 2.5% of the original contract amount.

 

Recommendation

rec

Staff recommends approval of Change Order No. 2 to the construction contract (COF Contract No. 2012-0145) with Brown Builders, Inc. for the intersection of State Route 252 (Wilson Pike) and McEwen Drive.