File #: 15-0890    Version: 1 Name:
Type: Contract/Agreement Status: Passed
File created: 9/21/2015 In control: Work Session
On agenda: 10/13/2015 Final action: 10/13/2015
Title: *Consideration of Amendment No. 2 to the TDOT Contract No. 110291 (COF Contract No. 2011-0129) for the Franklin ITS Extension (TDOT PIN 116144.00) and Adaptive Signal Control Technology (TDOT PIN 116144.01) projects for a time extension and a redistribution of existing funds
Sponsors: Engineering
Attachments: 1. 116144.00 Amendment REVISED.pdf

 

DATE:                                                               October 13, 2015

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          David Parker, City Engineer/CIP Executive

                                          Paul Holzen, Director of Engineering

                                          Jonathan Marston, Engineer 3                     

                                          

SUBJECT:                                          

title

*Consideration of Amendment No. 2 to the TDOT Contract No. 110291 (COF Contract No. 2011-0129) for the Franklin ITS Extension (TDOT PIN 116144.00) and Adaptive Signal Control Technology (TDOT PIN 116144.01) projects for a time extension and a redistribution of existing funds

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Amendment No. 2 to the Tennessee Department of Transportation (TDOT) Contract No. 110291 (COF Contract No. 2011-0129) for the Franklin Intelligent Transportation System (ITS) Extension (TDOT PIN 116144.00) and Adaptive Signal Control Technology (ASCT) (TDOT PIN 116144.01) projects for a time extension and a redistribution of existing funds.

 

Background

On September 13, 2011, the BOMA approved the TDOT Contract No. 110291 (COF Contract No. 2011-0129) for the Franklin ITS Extension project (TDOT PIN 116144.00).  The original project had a total budget of $2,500,000 at an 80/20 match, with the City’s financial obligation being $500,000.  The original intent of this project was to expand the City’s ITS infrastructure, per the Franklin ITS Master Plan, which was approved by the BOMA on January 26, 2006.  The original contract had a completion date of December 31, 2015 with a funding distribution as follows:

 

PHASE                     FUNDING SOURCE                     FED %                     STATE %                     LOCAL %                     ESTIMATED COST

PE-NEPA                     L-STP                     80                     0                     20                     $ 200,000.00

PE-DESIGN                     L-STP                     80                     0                     20                     $ 300,000.00

CONSTRUCTION                     L-STP                     80                     0                     20                     $ 1,920,000.00

OVERSIGHT                     L-STP                     80                     0                     20                     $ 80,000.00

 

On June 11, 2013, the BOMA approved Amendment No. 1 to the TDOT Contract No. 110291 (COF Contract No. 2011-0129).  This amendment added “adaptive signal control” to the list of accepted work types and created a child project (TDOT PIN 116144.01) for the “implementation” of adaptive signal control technology (ASCT).  The overall funding level of $2,500,000 remained the same, but the funding distribution changed as follows:

 

 

TDOT PIN 116144.00 - Franklin ITS Extension

PHASE                     FUNDING SOURCE                     FED %                     STATE %                     LOCAL %                     ESTIMATED COST

PE-NEPA                     STP                     80                     0                     20                     $ 200,000.00

PE-DESIGN                     STP                     80                     0                     20                     $ 300,000.00

CONSTRUCTION                     STP                     80                     0                     20                     $ 1,170,000.00

OVERSIGHT                     STP                     80                     0                     20                     $ 80,000.00

 

TDOT PIN 116144.01 - Adaptive Signal Control Technology (ASCT)

PHASE                     FUNDING SOURCE                     FED %                     STATE %                     LOCAL %                     ESTIMATED COST

IMPLEMENTATION                     STP                     80                     0                     20                     $ 750,000.00

 

Since the approval of this amendment, design work has begun on both the Franklin ITS Extension and the Adaptive Signal Control Technology projects.  Because of staff turnover and the level of detail required by both projects, City staff has requested a time extension of one (1) year from TDOT.  Also, as the design of the ASCT project has progressed, it has become apparent that this project will require a larger portion of funding than provided in the Amendment No. 1 distribution.  TDOT Local Programs Staff have bundled both the time extension to December 31, 2016 and funding redistribution requests into Amendment No. 2, which has a funding distribution as follows:

 

TDOT PIN 116144.00 - Franklin ITS Extension

PHASE                     FUNDING SOURCE                     FED %                     STATE %                     LOCAL %                     ESTIMATED COST

PE-DESIGN                     STP                     80                     0                     20                     $ 150,000.00

CONSTRUCTION                     STP                     80                     0                     20                     $ 670,000.00

TDOT ES                     STP                     80                     0                     20                     $ 80,000.00

 

TDOT PIN 116144.01 - Adaptive Signal Control Technology

PHASE                     FUNDING SOURCE                     FED %                     STATE %                     LOCAL %                     ESTIMATED COST

PE-DESIGN                     STP                     80                     0                     20                     $ 350,000.00

IMPLEMENTATION                     STP                     80                     0                     20                     $ 375,000.00

CONSTRUCTION                     STP                     80                     0                     20                     $ 875,000.00

 

Financial Impact

This amendment causes no additional financial impact to the City of Franklin.  Both projects have been funded in the Engineering-TOC annual operating budget.

 

Recommendation

rec

Staff recommends approval of Amendment No. 2 to TDOT Contract 110291 (COF Contract No. 2011-0129).