File #: 15-0659    Version: 1 Name:
Type: Report Status: Passed
File created: 7/13/2015 In control: Capital Investment Committee
On agenda: 7/23/2015 Final action: 7/23/2015
Title: Stormwater Projects Status Report
Sponsors: Engineering

 

DATE:                                                               July 23, 2015

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          David Parker, City Engineer/CIP Executive

                                          Paul Holzen, Director of Engineering                     

                                          

SUBJECT:                                          

title

Stormwater Projects Status Report

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City’s stormwater projects.

 

Project Status

rec

A.                     Jackson Lake Dredging Improvements

Key Dates: Design Start - 9/9/2008; Design Completion - June 2010; Bid Date - February 15, 2011; Construction Start - May 2, 2011; Construction Completion - September 2015

Cost: Design - $69,400.00; Construction - $1,663,931.73

Status Update: Contractor has removed most of the sediment from the dewatering area. Project will be completed by September 2015

 

B.                     100-Block Battle Avenue Drainage Improvements

Key Dates: Design Start - July 24, 2012 (BOMA Approved); Design Completion - August 2015*; Easement Acquisition Start - August 2015*; Easement Acquisition Completion - January 2016*; Bid Date - February 2016*; Construction Start - March 2016*; Construction Completion - August 2016*

*Denotes Estimated Dates

Cost: Initial Study - $46,500.00; Final Design - $131,700.00 (Including Amendment 1 of $68,200.00); Construction Estimate- $1,200,000.00

Status Update:  The BOMA approved moving forward with the project on December 9, 2014.  Amendment No. 1 to the design contract (COF Contract No. 2013-0180) was approved at the April 28TH BOMA meeting.  This amendment allows for completion of final design.     

 

C.                     Figuers Drive and 400-Block Battle Avenue Drainage Improvements

Key Dates: Design Start - November 26, 2013 (BOMA Approved); Design Completion for Preliminary Design- November 2014; Easement Acquisition Start - TBD; Easement Acquisition Completion - TBD; Bid Date - TBD; Construction Start - TBD; Construction Completion - TBD;

Cost: Initial Design - $82,000.00; Final Design - TBD; Construction - TBD (engineering estimate)

Status Update:  Final preliminary design is complete and was presented to the BOMA in March.  The final design PSA with our consultant, Neel-Schaffer, is on the July 23RD CIC agenda.    

 

D.                     Ralston Creek (Cheswicke Farms) Stream Restoration

Key Dates: Design Start - July 2013; Design Completion - December 2014; Bid Date - January 13, 2015; Construction Start - August 2015*; Construction Completion - October 2015*

*Denotes Estimated Dates

Cost: Design - $57,050.00; Construction - $89,061.00 (bid amount)

Status Update:  The bid opening for construction of this project was held on January 13, 2015.  The City received 2 bids.  Resolution 2015-23 to award this construction contract (COF Contract No. 2014-0303) to Viking Products, Inc., the apparent low bidder, was on the May 12TH BOMA meeting agenda.  As soon as the contract is signed and the new ARAP is received, work can begin.