Skip to main content
File #: 15-0986    Version: 1 Name:
Type: Report Status: Agenda Ready
File created: 10/16/2015 In control: Capital Investment Committee
On agenda: 10/29/2015 Final action:
Title: Stormwater Projects Status Report
Sponsors: Engineering
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

DATE:                                                               October 29, 2015

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                                               David Parker, City Engineer/CIP Executive

                                                                 Paul Holzen, Director of Engineering

                     

SUBJECT:                                          

title

Stormwater Projects Status Report

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City’s stormwater projects.

 

Project Status

A.                     Jackson Lake Dredging Improvements

Key Dates: Design Start - 9/9/2008; Design Completion - June 2010; Bid Date - February 15, 2011; Construction Start - May 2, 2011; Construction Completion - October 2015

Cost: Design - $69,400.00; Construction - $1,663,931.73

Status Update: Contractor has removed all of the sediment from the dewatering area. Contractor continues clean-up work.

 

B.                     100-Block Battle Avenue Drainage Improvements

Key Dates: Design Start - July 24, 2012 (BOMA Approved); Design Completion - January 2016*; Easement Acquisition Start - March 2016*; Easement Acquisition Completion - July 2016*; Bid Date - August 2016*; Construction Start - September 2016*; Construction Completion - March 2017*

*Denotes Estimated Dates

Cost: Initial Study - $46,500.00; Final Design - $131,700.00 (Including Amendment 1 of $68,200.00); Construction Estimate- $1,200,000.00

Status Update:  The BOMA approved moving forward with the project on December 9, 2014.  Amendment No. 1 to the design contract (COF Contract No. 2013-0180) was approved at the April 28TH BOMA meeting.  This amendment allows for completion of final design.  Updated survey completed in July.  Geotechnical explorations were completed at the end of September.  The final design will continue in October, with anticipated completion in January 2016.  ROW Acquisition could begin in early Spring 2016.

 

C.                     Figuers Drive and 400-Block Battle Avenue Drainage Improvements

Key Dates: Design Start - November 26, 2013 (BOMA Approved); Design Completion for Preliminary Design- November 2014; Easement Acquisition Start - TBD; Easement Acquisition Completion - TBD; Bid Date - TBD; Construction Start - TBD; Construction Completion - TBD;

Cost: Initial Design - $82,000.00; Final Design - $125,200.00; Construction - TBD (engineering estimate)

Status Update:  Final preliminary design is complete and was presented to the BOMA in March.  The final design PSA with our consultant, Neel-Schaffer, was approved by BOMA on August 26, 2015, for $125,200.00.  Final Design survey was completed in October.  Design will continue into the spring. 

 

D.                     Ralston Creek (Cheswicke Farms) Stream Restoration

Key Dates: Design Start - July 2013; Design Completion - December 2014; Bid Date - January 13, 2015; Construction Start - August 24, 2015; Construction Completion - October 23, 2015

Cost: Design - $57,050.00; Construction - $89,061.00 (bid amount)

Status Update:  Bulk of construction is complete.  Contractor will return later for final site stabilization and planting of trees.