File #: 15-0579    Version: 1 Name:
Type: Report Status: Passed
File created: 6/15/2015 In control: Capital Investment Committee
On agenda: 6/25/2015 Final action: 6/25/2015
Title: Water and Sewer Projects Status Report
Sponsors: Engineering
 
DATE:                  June 25, 2015
 
TO:            Board of Mayor and Aldermen
 
FROM:            Eric Stuckey, City Administrator
            David Parker, City Engineer/CIP Executive
            Mark Hilty, Director of Water Management
            Paul Holzen, Director of Engineering      
            
SUBJECT:            
title
Water and Sewer Projects Status Report
 
body
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's water and sewer projects.
 
Project Status
A.      Spencer Creek Basin - South Prong Interceptor Upgrade
Key Dates: Design Start - April 23, 2013; Design Completion - June 2015*; Bid Date: Not Funded; Construction Start - Not Funded; Construction Completion - Not Funded
*Denotes Estimated Date
Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded
Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD
Status Update:  Design plans are currently underway, but the project will not be constructed until funding is available from the Water Management Department budget.
 
B.      Charlton Green Sanitary Sewer Improvements
Key Dates: Design Start - November 12, 2013; Design Completion - March 2014; Bid Date:  April 7, 2014; Construction Start - December 1, 2014; Construction Completion - April 2015
Cost: Design - $19,895.00; Easement - $3,500.00; Construction -$465,304.90
Funding Source: Design -Sewer Operating; Construction - Sewer Fund
Status Update:  The final change order is on the June 2015 CIC meeting agenda.
      
C.      Spencer Creek at Franklin Road Sewer
Key Dates: Design Start - March 11, 2014; Design Completion - June 2015*; Easement Acquisition Start - June 2015*; Easement Acquisition Completion - August 2015*; Bid Date: September 2015*; Construction Start - November 2015*; Construction Completion - April 2016*
      *Denotes Estimated Date
Cost: Design - $40,000.00; Easement - TBD; Construction - TBD
Funding Source: Design - Sewer Fund
Status Update:  The SWPPP has been signed and submitted to TDEC for approval.  The TDOT permit to cross Franklin Road has been approved.  The CSX permit package was received on May 28, 2015, and has to be reviewed by the Legal Department.  TDEC has approved the construction plans.  Easement documents have been completed.
 
D.      Curd Branch and Watson Branch Interceptor Sewer
Key Dates: Design Start - February 25, 2014; Design Completion - March 2015; Easement Acquisition Start - February 2015; Easement Acquisition Completion - June 2015*; Bid Date: August 2015*; Construction Start - September 2015*; Construction Completion - August 2016*
*Denotes Estimated Date
Cost: Design - $115,000.00; Easement - TBD; Construction - TBD
Funding Source: Design - Sewer Fund
Status Update:  Plans have been submitted to TDEC for approval.  The easement acquisition process is continuing.  The ARAP application has been submitted for review and approval.
 
E.      Fieldstone Farms Pump Station No. 1 Rehabilitation
Key Dates: Design Start - January 14, 2014; Design Completion - November 2014; Bid Date: December 11, 2014; Construction Start - June 2015*; Construction Completion - June 2016*
*Denotes Estimated Date
Cost: Design - $226,848.00; CEI - $196,000.00; Construction - $1,592,000.00
Funding Source: Design - Sewer Fund; Construction - Sewer Operating Fund
Status Update:  Staff is finalizing the contract documents.  The contractor is looking to start work around the last part of June 2015.
 
F.      Sanitary Sewer System Model and Capacity Assurance Tool - Phase 1
Key Dates: Design Start - March 11, 2014; Design Completion - April 2015
Cost: Design - $182,000.00
Funding Source: Design - Sewer Fund
Status Update:  The engineer is working on completing the data needed to run the model.  The tool has been delivered to the City for use.   
 
G.      Goose Creek Sanitary Sewer Extension Project from West of I65 to the East Side of I65
Key Dates: Design Start - September 9, 2014; Design Completion - April 2015; Easement Acquisition Start - July 2015*; Easement Acquisition Completion - September 2015*; Bid Date: November 2015*; Construction Start - January 2016*; Construction Completion - July 2016*
*Denotes Estimated Date
Cost: Design - $120,725.00; Easement - TBD; Construction - TBD
Funding Source: Design, Easement, Construction - Sewer Fund & HPT TA Properties Trust
Status Update:  Staff has met with the consultant to discuss revisions to the design plans prior to submittal to TDEC.