Legislation Details

File #: 17-0755    Version: 1 Name:
Type: Contract/Agreement Status: Agenda Ready
File created: 8/17/2017 In control: Capital Investment Committee
On agenda: 8/24/2017 Final action:
Title: Consideration of DRAFT Road Impact Fee Offset Agreement (COF Contract No. 2017-0120) with Westhaven Partners, LLC for Intersection Improvements at SR-96W and Westhaven Boulevard/Old Charlotte Pike
Sponsors: Paul Holzen, Jonathan Marston
Attachments: 1. COF 2017-0120 - West Haven Traffic Signal RIF - Exhibit A.pdf, 2. COF 2017-0120 SL Road Impact Fee Agreement CLEAN.pdf

 

DATE:                                                               August 17, 2017

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Paul Holzen, Director of Engineering

                                          Jonathan Marston, Assistant Director of Engineering

                     

                                          

SUBJECT:                                          

title

Consideration of DRAFT Road Impact Fee Offset Agreement (COF Contract No. 2017-0120) with Westhaven Partners, LLC for Intersection Improvements at SR-96W and Westhaven Boulevard/Old Charlotte Pike

body

 

Purpose

The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning a Road Impact Fee Offset Agreement with Westhaven Partners, LLC for Intersection Improvements at SR-96W at Westhaven Boulevard/Old Charlotte Pike.

 

Background

As part of the Westhaven Development, the City has required the developer to make improvements to the intersection of SR-96W and Westhaven Boulevard/Old Charlotte Pike.  These improvements are identified in the City’s Compressive Transportation Network Plan and would qualify for a road impact fee offset. The project includes the installation of a new traffic signal and an additional left turn lane on Westhaven Boulevard.

 

Financial Impact

The Developer will be reimbursed Road Impact Fees paid.  Below is an estimate of the project cost:

 

$   35,000 - Design/Survey

$       0.00 - Right-of-Way Acquisition

$365,000 - Construction

$400,000 - Total Estimated Project Cost

 

Recommendation

rec

Staff recommends approval of COF Contract No. 2017-0120.