SPRING CREEK CENTER SUBDIVISION, SITE PLAN, SECTION 1, REVISION 4 (SPRING CREEK CENTER)
Maint agreement: Drainage $22,800
Established: August 27, 2015
Previous Action: 4/22/10 Reapproved by FMPC
8/18/10 PA posted
11/12/10 Reduce 75% from $228,000; extend to 11/11/11
11/11/11 Extend to 11/9/12
11/9/12 Approved extension to 5/17/13
5/17/13 Extend to 11/8/13
11/26/13 Approved extension to 5/22/14
4/24/14 Release denied; extend to 4/23/15; revise as-builts
12/12/14 Release denied; extend to 12/11/15
2/26/15 Release denied; extend to 2/25/16 (revise as-builts again, following completion of punchlist).
8/27/15 Release PA, establish MA for $22,800
10/19/15 MA posted
Recommendation: Release the maintenance agreement.