File #: 18-1239    Version: 1 Name: RES 2018-102 Design Direction 96 West Trail
Type: Resolution Status: Passed
File created: 11/29/2018 In control: Board of Mayor & Aldermen
On agenda: 4/23/2019 Final action: 4/23/2019
Title: Consideration of Resolution 2018-102, "A Resolution Providing Design Direction for the SR96 West Multipurpose Trail Project (Vera Valley Drive to 5th Ave North) (Deferred from 12/11/18 WS; 1/08/19 and 2/12/19 WS; 03/26/19 WS)
Sponsors: Vernon Gerth, Paul Holzen
Attachments: 1. Res 2018-102 - SR96 WEST TRAIL.Law Approved 3.pdf, 2. FLOWER SHOP EXHIBIT 2-27-2019.pdf, 3. Res 2018-102 - SR96 WEST TRAIL.Law Approved 3
DATE: March 22, 2019

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Vernon Gerth, Assistant City Administrator
Paul Holzen, Director of Engineering
Jonathan Marston, Assistant Director of Engineering

SUBJECT:
title
Consideration of Resolution 2018-102, "A Resolution Providing Design Direction for the SR96 West Multipurpose Trail Project (Vera Valley Drive to 5th Ave North) (Deferred from 12/11/18 WS; 1/08/19 and 2/12/19 WS; 03/26/19 WS)
body

Purpose
The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the design of the multipurpose trail project along State Route 96 West from Vera Valley Drive to 5th Avenue North, Resolution 2018-102.

body
Background
The City was awarded $1,800,000 in Federal Transportation Alternative Program (TAP) funds to help pay for the construction of a multi-use trail along the north side of SR-96 West between Vera Valley Drive and 5TH Avenue North. TDOT has told all TPA fund recipients that these funds need to be obligated with a Notice to Proceed for Construction on or before July 15, 2019 or funds will be rescinded. Below is a summary of the project status:
* NEPA (Environmental Phase) - 100% Complete and approved by TDOT
* Right-of-Way - 90% Complete with agreements of sale on 16 out of 18 tracts. The remaining tracts have been submitted for condemnation.
* Design - 95% Complete and submitted to TDOT
* Utility Coordination - 80% Complete

Staff is currently on schedule to meet the funding obligation deadline. Below is a summary of the current and estimated project cost:


Current Cost
Estimated Total
Design
$159,319.91
$175,000.00
Appraisals / Acquisition
$175,881.92
$216,800
Right-of-Way / Easements
$334,750.00
$500,000
Estimated Construction
$0.00
$3,693,900
Total
$669,951.80
$4,585,700