Title: Consideration of Final Change Order to the Construction Contract (COF Contract No. 2015-0062) for the Water Treatment Plant Modifications Project with Judy Construction, Inc. for a Cost DECREASE of $79,790.00 and a Time Reduction of 15 days (01/24/19 CIC 4-0)
Sponsors: Michelle Hatcher
Attachments: 1. 2015-0062 WTP Final Reconciling Change Order

DATE: November 13, 2018

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Mark Hilty, Assistant City Administrator for Public Works
Michelle Hatcher, Director of Water Management
Patricia McNeese, Utilities Engineer II

SUBJECT:
title
Consideration of Final Change Order to the Construction Contract (COF Contract No. 2015-0062) for the Water Treatment Plant Modifications Project with Judy Construction, Inc. for a Cost DECREASE of $79,790.00 and a Time Reduction of 15 days (01/24/19 CIC 4-0)

body
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the final change order to the Construction Contract (COF Contract No. 2015-0062) for the Water Treatment Plant Modifications Project.

Background
On August 25, 2015, the BOMA approved the construction contract with Judy Construction for the Water Treatment Plant Modifications Project. The original project had a total budget of $14,018,000.00 and 730 calendar days to be substantially complete. BOMA approved Change Order No. 1 on August 9, 2016 with a total decrease of $171,937.53 to the overall budget and an addition of 56 days to the contract. Change Order No. 2 was approved by the BOMA with a decrease of $21,700.00 to the overall budget and an addition of 92 days to the contract. On May 8, 2018 the BOMA approved Change Order No. 3 which added 48 calendar days to the contract.

The Final Change Order details include the following:

1. Final reconciliation and balancing of all contract line item overruns and underruns
2. Time extension total of 181 days to the contract for a contract total of 911 calendar days.

Financial Impact
This final change order is a decrease of $79,790.00 to the original contract.

Recommendation
rec
Staff recommends approval of the Final Change Order to the Construction Contract (COF Contract No. 2015-0062) for the Water Treatment Plant Modifications Project with Judy Constru...