File #: 18-1219    Version: 1 Name:
Type: Report Status: Passed
File created: 11/19/2018 In control: Capital Investment Committee
On agenda: 11/29/2018 Final action:
Title: Water and Sewer Projects Status Report
Sponsors: Michelle Hatcher, Patricia McNeese

DATE: November 19, 2018

TO: Board of Mayor and Aldermen

FROM: Eric Stuckey, City Administrator
Mark Hilty, Assistant City Administrator for Public Works
Michelle Hatcher, Director of Water Management
Patricia McNeese, Utilities Engineer II


SUBJECT:
title
Water and Sewer Projects Status Report
body
Purpose
The purpose of this memo is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning the status of some of the City's water and sewer projects.

Project Status

A. Spencer Creek Basin - South Prong Interceptor Upgrade
Key Dates: Design Start - April 23, 2013; Design Completion - February 2017*;
Easement Acquisition - TBD; Construction - Not Funded
*Denotes Estimated Date
Cost: Design - $337,000.00; Easement - Not Funded; Construction - Not Funded
Funding Source: Design - Sewer Fund; Easements - TBD; Construction - TBD
Status Update: Plans are complete but will not be submitted to TDEC for approval until the project is closer to bid. Easement documents have been prepared and submitted to City Staff for review. The project will not be constructed until funding is available from the Water Management Department budget.

B. Spencer Creek at Franklin Road Sewer
Key Dates: Design Start - March 11, 2014; Design Completion - June 2015; Easement Acquisition Start - September 2015; Easement Acquisition Completion - December 2018*; Bid Date: March 2019*; Construction Start -May 2019*; Construction Completion - December 2019*
*Denotes Estimated Date
Cost: Design - $40,000.00; Construction - TBD
Funding Source: Design - Sewer Fund
Status Update: The plans are 100% complete. Three of the four easements required have been obtained; the last easement is still in negotiation. The project will be bid once the easement has been obtained.


C. Bobby Drive Water Line Improvement Project
Key Dates: Design Start - May 12, 2015; Design Completion - April 2016; Easement Acquisition Start - June 2016; Easement Acquisition Completio...