File #: 18-0681    Version: 1 Name: DEMO of 403 and 405 Hillsboro Road The Hill
Type: Resolution Status: Passed
File created: 6/28/2018 In control: Work Session
On agenda: 7/10/2018 Final action: 7/10/2018
Title: *Consideration of Resolution 2018-55, "A Resolution Awarding the Construction Contract (COF Contract No. 2018-0052) to Renascent, Inc. in the Amount of $30,829.16 for the Demolition of Structures Located at 403 and 405 Hillsboro Road".
Sponsors: Brad Wilson, Paul Holzen
Attachments: 1. Res 2018-55 - Hill Property Demo.Law Approved.pdf

DATE:                                          June 21, 2018

 

TO:                                          Board of Mayor and Aldermen

 

FROM:                                          Eric Stuckey, City Administrator

                                          Vernon Gerth, Assistant City Administrator - Community/Economic Development

                                          Brad Wilson, Facilities Project Manager

                                          Paul Holzen, City Engineer/Director of Engineering

                                          

SUBJECT:                                          

title

*Consideration of Resolution 2018-55, “A Resolution Awarding the Construction Contract (COF Contract No. 2018-0052) to Renascent, Inc. in the Amount of $30,829.16 for the Demolition of Structures Located at 403 and 405 Hillsboro Road”.

body

 

Purpose

The purpose of this memorandum is to provide information to the Franklin Board of Mayor and Aldermen (BOMA) concerning Resolution 2018-55.

 

Background

The City property, which is located at 403 and 405 Hillsboro Road, has reached an end regarding its need and usefulness to the City of Franklin.  The facility is no longer safe for personnel to utilize the facility for work and/or training, and the amount of funds required for rehabilitation or refurbishment has been deemed too costly.  On May 30, 2019, sealed bids were received by Facilities at City Hall and were publicly opened and read aloud for the 405 and 403 Hillsboro Road Demolition Project (COF 2018-0052).  The low bidder was Renascent, Inc.

 

Financial Impact

Renascent, Inc. was the low bidder on the project in the amount of $30,829.16.

 

Recommendation

rec

Staff recommends approval of Resolution 2018-55.